Chestnut Street Bridge Active Transportation Enhancements

The developments on each side of the Rock River along the Chestnut/Walnut Street corridor makes this bridge not only a vital connection for vehicles, but for cyclists and pedestrians as well.  This project will include engineering and construction of a more active transportation friendly facility along the bridge, providing a  safer barrier between vehicles and other roadway users.  The project is to be designed and constructed in 2018, using Motor Fuel Tax funds.

Current Status Design Engineering
Lead Agency City of Rockford
Tentative Construction Letting Date Summer 2018
Estimated Project Cost Design- $150,000
Construction- $300,000
Construction Engineering- $100,000
Total- $400,000
Funding Source Motor Fuel Tax
Estimated Completion Date Winter 2018